The radiators arrived today. 9 out of 11 survived the pressure testing. We went for gun metal grey and they look great.
The roof insulation is all in. We have 7 different roof spaces but as half of them had no access new holes had to be created to get the insulation in and then filled back up. We now have a thick blanket of wool above our heads which has surely got to make a difference…
However the plans for the biomass installation (See Preparing for next winter – Apr 7) have been seriously delayed. The council planners said to estimate 3 months so I doubled it and crossed my fingers that it would be in before Christmas. It’s tight. The man from the council is coming next week and it’s a 5 week lead on the boiler….